3rd Edition PMI Program Management Guide Comments
Notification from PMI Regarding The Standard for Program Management—Third Edition
Thank you for participating in The Standard for Program Management—Third Edition Exposure Draft process. Below you will find a list of the recommendations that you have made and the committee’s decision for each of your recommendations. If you have any additional questions or comments you can contact Kristin Vitello at Kristin.Vitello@pmi.org.
If you are unsatisfied with the final decision made by the committee you have the opportunity to appeal. You will have until Thursday, 19 April 2012 to do so. Click on the “Go to Exposure Draft” link provided below for more information.
Go to Exposure Draft
Adjudication will end on: 5/3/2012
OriginalText
1
The Standard for Program Management
Your Recommendation
Retitle: A guide to….
Your Justification
This document is neither “THE” nor a “STANDARD”.
Our vote on your recommendation: Deferred
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. This recommendation has been deferred, as it is out of scope for current update committee’s project charter. Your recommendation will be forwarded to next update committee for their consideration.
OriginalText
1
The Standard for Program Management
Your Recommendation
Consider with care the role of “program” and redraft the document to reflect insight that better serves organisations. As written the guidance has some profoundly wrong perspectives that twist many many elements of the whole into something that is short of what it could be. It is important that you get this as right as it is currently possible to be, the influence the pmi weilds means other sources of guidance are chocked off – the world is deprived of better insight by the very fact that you publish this with flaws. Clearly being comissioned to write on programs has cause the authoring team some difficulties – Program is a nebulous concept without obvious and easily defended attributes – this has led to the authoring team grabbing ever possible program related concept and exagerating its importance and eclusivity. Please experiment by adopting pro-temp the view that there is no such concept as program, just projects of varying size and uncertainty, take the view that every project MUST have effort expended to deliver benefits and that all project and non-project activity comprises the portfolio – now see how much “program” guidance remains and how much claimed as program is just project and operational business.
Your Justification
many of my points can be linked to specific quotes from your draft – it is too onerous through this mechanism to link them – please cast your mind across the first 1,000 lines and I will note them as I go line by line (but not try to list them here). A project is a collection of coordinated activities that together deliver change to a system (organisation). A portfolio is the collection of all activity undertake by an organisation whether change oriented or business as usual (bau). These two points can be argued and tweaked but are essentially stable start-points. There are two undeniable concepts – project and portfolio Any enterprise is constituted with some form of accepted operating principles (governance – written or not) that is understood by those touched by its existance in any fashion. In general these say that the officers of teh company have a duty to protect those involved: society, workforce, consumers, shareholders(equity), bankers(debt)… As writen about in documents like the PMBoK Guide a project is described from a supplier’s perspective – temporary, delivers a result. As seen from the perspective of the enterprise’s officers it is an investment in change to BAU. The project is a set of activities that is PART of a change from current benifits realisation activity to future state with an amended portfolio of beneficial activity. What you call a project is actually in the eyes of those with a duty of care what you call a program. Problems arise as a result: The document under review is describe guidance for programs with a blinkered view that is pureley the viewpoint from the supplier’s domain. It is appropriate to wrap some projects in a common governance structure but your failure to differentiate what is program in supplier terms and activity to generate benefit from project in investor terms has coloured everything else written in this guide to be one-sided and weakened. As I go i’ll point out its affect on individual lines – each is individually small but there are so many the total effect is large, pervasive and sadly saps value from the end result. Simon@logicalmodel.net
Our vote on your recommendation: Deferred
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. This recommendation has been deferred, as it is out of scope for current update committee’s project charter. Your recommendation will be forwarded to next update committee for their consideration.
OriginalText
5
1 Introduction
Your Recommendation
Review the whole document to remove tautology
Your Justification
many sentences use adjectives and express their meanings twice. They lengthen the document, add ambiguity and reduce clarity. For non native English speakers you leave them wondering if the dupication is expansion of concepts so you reduce their understanding. You not only have to have a clear view of what worthy practices are you have to be able to express them
with clarity. It takes less wrords and more effort than has been included and spent so far
Our vote on your recommendation: Editorial
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The core committee has reviewed your recommendation and determined that the recommendation is editorial and not substantive. This request will be forwarded to the editorial department for possible inclusion.
OriginalText
40 defines a program as “a group of related projects managed in a coordinated way to obtain
Your Recommendation
Consider if programs really exist, if so find a meaningful definition that is both inclusive of what IS a program and exclusive of what is not a program – as it stands the definition that is given fails any test. You cannot create dependable guidance without dependable foundations
Your Justification
A project is a collection of activities managed in a coordinate way to obtain benefits and control not available whne managing them individually – indesputably a project fits your program definition – oh sh*t! and now the problems start. With a definition that is not what we need then the arguments/ justifications/ conculsions that follow are at best unsafe and at worst selectively (“economically”) presented
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The definition throughout the standard will reflect PMI’s Lexicon definition for Program: This line will be revised as follows: “A group of related projects, subprograms, and program activities, managed in a coordinated way to obtain benefits not available from managing them individually.”
OriginalText
42 program are related through a common goal. If the projects have separate goals and are
Your Recommendation
Find and use a clear, justifiable definition of program
Your Justification
both what you describe as program and what is known as project are described by “a collection of work-packages all of which are necassary and none of which is individually sufficient to deliver benefits” in a project work-packages may (or may not be) 80hrs effort. In a program are they projects? in a 80 work-package are they one person’s work in one shift? I suggest *if* programs exist in a manner useful to isolate and describe then their definition is best phrased in the means of their control during execution not their contribution to balance sheets and P&Ls which you repeatedly define as “strategy” but that is assumption not fact
Our vote on your recommendation: Accepted With Modification
Our justification: Accept with Mod Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The sentence has been revised as follows: “… programs are related through a common goal, often of strategic importance to the sponsoring organizaiton.”
OriginalText
47 The Standard for Program Management is an important and essential link in understanding
Your Recommendation
delete one of “important” or “essential”
Your Justification
if it is “essential” it must be “important” – tautology is undesirable in a document whose purpose is “standard” and “global”. If you aim is to improve capability and communicate across mother-tounge barriers simplify the langauge here and everywhere – if your writing a book to make money without regard to sagacity, veractity (etc) then how does that square with teh code of ethics!?
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The phrase has been revised as follows: “”The Standard for Program Management is an important link in understanding…”
OriginalText
49 management. Program management also enhances the delivery capabilities of the sponsoring
Your Recommendation
delete assertion that pgm mgmt enhances organisations – or cite the proof
Your Justification
Even research publishe in PMI journals is unable to establish a link to PMP status or PMBoK Guide use to improved results – can you justify improvements in something less concrete than projects when projects are stil in debate!? Guidance has to be realistic and reliable before practitioners can use what is trustworthy and fill gaps in what is still less well understood
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The sentence has been removed.
OriginalText
51 program management that is clear, complete, relevant, and generally recognized as good
Your Recommendation
delete “complete”
Your Justification
you cannot, ethically, claim to have written anything that is complete
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The phrase has been revised as follows: “It provides information on program management that is generally recognized…”
OriginalText
65 of program management among the following groups to promote efficient and effective
Your Recommendation
delete “efficient”
Your Justification
effective is viable but a project, let alone a collection of them has to be responsive and that is never(!) achieved by optimising some capabilities over others – projects are reactive – the anathma of efficient
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows:In addition, this standard provides a common lexicon leading to a understanding of program management among the following groups to promote effective communication and coordination:
OriginalText
73 • Stakeholders, to understand the role of program managers and how they engage the
Your Recommendation
replace “stakeholders” with “everyone with an interest”
Your Justification
Your own use of S/H begs questions of who is included and excluded. The PMBoK Guide 5th Ed manages to define stakeholders as “everyone” and you also need to propogate the definition as “everyone, whether affected or able to affect, whether interested or not”
Our vote on your recommendation: Deferred
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – The team who created the document came from a varied background including several from the government sector who have interest in large government initiatives. The team worked to make the text applicable to most programs most of the time. Your recommendation will be forwarded to next update committee for their consideration.
OriginalText
76 the program governance board/steering committee, to precisely document the intended
Your Recommendation
delete ‘precise’
Your Justification
you cannot claim or suggest precision applies in anything project, let alone program linked
Our vote on your recommendation: Accepted
Our justification:
OriginalText
88 This introductory chapter provides an overview of The Standard for Program Management by
Your Recommendation
delete or move and merge with the first time the chapter’s purpose was described
Your Justification
fragmentation of the chapter’s purpose over several similar but different words and hence meanings weakens guidance
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments,this paragraph will be moved to beginning of seciton.
OriginalText
100 regulations, and organizational and professional policies. Since practitioners come from
101 diverse backgrounds and cultures, the Code of Ethics and Professional Conduct applies
102 globally. When interacting with stakeholders, practitioners must be committed to honest
Your Recommendation
reword to be correct – it is not the diversity of reader’s ethnicity that makes the guidance widely applicable but the reader’s diversity causes the need to be inclusive – it is vital that you write what you mean and mean what you write if guidance is to reliable – you don’t/ arent and it isn’t
Your Justification
pmi reach means everyone else’s ability to make serious inroads to influencing thinking is hugely depressed – your killing evolution of good thinking so we are all dependant on you upping your game on what you publish – the thinking is sloppy and partisan. It is capable of significant improvement. your not on the cutting edge of thinking and your not representative of what a well informed boardroom would recognise and that is reprehensible. you must take responsibility (under the ethics code if for no other reason) to be correct in facts and representative of opinions where facts are not possible
Our vote on your recommendation: Editorial
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The core committee has reviewed your recommendation and determined that the recommendation is editorial rather than substantive. This request will be forwarded to the editorial department for possible inclusion.
OriginalText
107
1.2 What Is a Program?
Your Recommendation
Reword the section to provide an answer to the question its heading proposes – at present youdo not answer the question.
Your Justification
While a program may be to paraphrase “coordinated activity managed together to deliver benefit not otherwise available” so to is a projet and so to is buiness as usual – to satisfy the title of this section in just “guidance” let alone “Standard” requires a definition that works to include what IS program AND works to exclude what is NOT program – you’ve fundamentally failed to provide adequate definition. From this flaw flows many errors in what follows – get it right – we neeed to provide reliable support to all those shareholders and tax payers who expect competent protection of their interests when managing organisation and societal change
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – The team who created the document came from a varied background including several from the government sector who have interest in large government initiatives. The team worked to make the text applicable to most programs most of the time. We do believe the current definition is representative for the current publication and was widely vetted. Your recommendation will be forwarded to next update committee for their consideration.
OriginalText
110 coordinated way to obtain benefits not available from managing them individually.
Your Recommendation
Rewrite the section in one of two ways – or both 1) advise the reader that the definition is from the supplier’s perspective only or 2) properly consider that a total perspective of program must exclude what isn’t program as well as include what is
Your Justification
Every PROJECT ever executed has a pre and post project set of activities that define it and use its outputs to generate benefits. Every project is a collection of activity. All you are doing here is seeing a project from the customer’s view point and claiming a supplier’s interest in selling related services This standard has profound difficulty being meaningful because it pretends there is a topic here. all it is doing is seeing projects from the business perspective of idea, development, integration to operations. you have a profoundly important duty as standards writers to apply correct thinking and description to the nature of project based change. you get the guidance right when you get the foundational principals correct and build on them. Principle-1 is that the business defines and owns change, it maybe useful for them to have support, the support they need must see their world clearly to understand what needs doing Principle-2 is that there there are multiple axis of interest one is leadership and management, one is what vs how, others are value vs cost, certainty vs uncertainty, prioritisation of resource allocation…
Our vote on your recommendation: Deferred
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – The team who created the document came from a varied background including several from the government sector who have interest in large government initiatives. The team worked to make the text applicable to most programs most of the time. The current definition stated in the exposure draft matches the definition from PMI’s Lexicon. Your recommendation will be forwarded to next update committee for their consideration.
OriginalText
112 A program is a group of related projects managed in a coordinated way to obtain benefits
Your Recommendation
delete
Your Justification
repeats 109 so adds lengtn but does not add value/ clarity – indeed for non-native-english readers repetition in alternate words often adds confusion
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised: We have deleted the redundant content and harmonized the definition to be consistent across the document.
OriginalText
114 various components—the majority of these being the individual projects within the program.
Your Recommendation
clarify meaning at present it says most of eth components are projects where as the turth would be most of the effort spent is consumed by projects – most of the actions by type are probably not projects they are controls
Your Justification
as above
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
124 enhancing current capabilities, or developing new capabilities for the organization,
125 customers, or stakeholders. A benefit is an outcome of actions, behaviors, products, or
126 services that provide utility to the sponsoring organization as well as to the program’s
127 intended beneficiaries or audience. To reinforce this important point, programs provide
128 organizations with the ability to deliver benefits to stakeholders, beneficiaries, or
129 customers, while at the same time delivering benefits (in the form of profitability or
130 business value) to the sponsoring organization.
Your Recommendation
Delete or reword to clarify what it is that is PROGRAM – as written one could substitute “operations” and the scentence would still be valid – this is not helpful in a section whose purpose is to isolate theefinition of program as a foundation to build guidance for their effective management
Your Justification
When you folk get these things wrong an army of less insightful people are prevented from moving forward because they won’t argue with your published words – you do double the damage when your insight is flawed to when you say nowt.
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the sentence has been revised as follows: “Programs and projects deliver benefits to organizations by generating business value, enhancing current capabilities, facilitating business change, maintaining an asset base, offerring new products and services to the market, or developing new capabilities for the organization…”
OriginalText
134 the duration of the program, or may be delivered all at once at the end of the program.
Your Recommendation
reword to clarify your point
Your Justification
as written this applied to a project yet your currently trying to isolate teh definition of program
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. The submitter provided no alternate or recommended text.
OriginalText
144 and close of the program. The space shuttle program can be viewed as an example of unified
Your Recommendation
choose an example that is unambigious
Your Justification
Was the space shuttle program from end of Appollo to the last flight this year of the last shuttle or upto the first shuttle flight – was the program only those fights after the development. Since before first shuttle flight a series of work-packages where in train with a very clear goal – reusable vehicle the shuttle’s development was only and example of a big project, and the missions taht run from first to last ‘operational flight’ are easily described as a program whose connected result was the earning of revenue for nasa or eth creation of a us military capability or… The shuttle is a really poor example because there are so many differnt ways to envisage what your label is inclusive of and exclusice of. It is also a terribly parochial example.
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – The team who created the document came from a varied background including several from the government sector who have interest in large government initiatives including NASA. Ultimately our decision was to leave the content as it stands.
OriginalText
151
Your Recommendation
explain or replace with something meaningful
Your Justification
a picture for a pictures sake – it adds no value as presented. A benefits map with labels carfully chosen for self-evident meaning may add value here – this one does not
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this with the committee. Ultimately our decision was to leave the content as it stands. We do believe that the diagram adds value and this decision aligns with several comments which were submitted.
OriginalText
156 The relationship among portfolios, programs, and projects is such that a portfolio refers
Your Recommendation
Reword the section to reflect teh key elements of the items listed in teh title
Your Justification
The weak start above is now causing secondary weaknesses. A portfolio is all activity within some boundary – typically an organisations total human and financial capital as defined in employment law and accounting conventions. The portfolio’s activity can only be one of two types: first that which delivers the ongoing utility (eg servicing customers and making profits) – whose end is not envisaged on any specific event or date – we might call this ‘business-as-usual’ and second ‘change’. Change always has an envisaged end even if we lack ability to describe it at the start. The end is always anticipated even if undefinable in advance or at any specific time. Change ranges over two aspects of definition: what and how – these are the twin dimensions of Scope (that pmbok manages to screw-up by putting half of the use of decomposition in time management instead of having activity definition in scope where it belongs)
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
164 organization’s strategic plan by means of the organization’s portfolio.
Your Recommendation
162-164 reword to say what you mean
Your Justification
this is a circular definition. the portfolio’s components don’t have to be linked by stragetic plan – the portfolio will include tactical elements so “linked to the org’s strategic plan by the portfolio’ isn’t necessarily correct
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
166 As Figure 1-2 illustrates, organizational strategies and priorities are linked and have
167 relationships between portfolios and programs, and between programs and individual
168 projects. Organizational planning impacts the projects by means of project prioritization
169 based on risk, funding, and other considerations relevant to the organization’s strategic
170 plan. Organizational planning can direct the management of resources, and support for the
171 component projects on the basis of risk categories, specific lines of business, or general
172 types of projects, such as infrastructure and process improvement.
Your Recommendation
delete
Your Justification
adds words but without meaning – thus without value
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
169 based on risk, funding, and other considerations relevant to the organization’s strategic
Your Recommendation
if you don’t dlete the chunck then at least say what matters with clarity – reword to express that prioritisation is ALWAYS on margin eg NPV – surplus of VALUE over cost at an acceptable level of uncertainty
Your Justification
as written you (yet again) mention cost (funding) but not return – with this wrong mindset follows wrong guidance in the rest of the publication – you must get eth introduction correct and then extend they foundations with logical extension in order to provide usable guidance – currently the world as reflected in this publication is only that of the supplier not of the investor – you need both to be roundde and meet the obligations of teh ethics code
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
182 Components within a program are related through a common outcome or delivery of a
183 collective set of benefits. If the relationship among the projects is only that of a
184 shared client, seller, technology, or resource, the effort should be managed as a
185 portfolio of projects rather than as a program. In programs, it is important to integrate
Your Recommendation
Reflect this observation through the 180 lines before here and eth several thousand after – currently this nugget is not influencing the rest of the writing sufficiently
Your Justification
Many places in the publication muddy the definitions of pgm by claimin more to them than they have legitimate right to include
Our vote on your recommendation: Deferred
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. This recommendation has been deferred, as it is out of scope for current update committee’s project charter. Your recommendation will be forwarded to next update committee for their consideration.
OriginalText
187 this by working in five (5) interrelated and interdependent Program Management Performance
Your Recommendation
delete the number in brackets
Your Justification
it adds nothing. if you think “five” may not be understood by your reader ship you seriously need to question use of words like “lexicon”.
Our vote on your recommendation: Editorial
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The core committee has reviewed your recommendation and determined that the recommendation is editorial rather than substantive. This request will be forwarded to the editorial department for possible inclusion.
OriginalText
205 Through structured oversight and governance, program management enables appropriate
Your Recommendation
and et seq tp 210 – Delete or reword to say something meaningful: What is “Structured oversight” and “optimised pacing” – if these things are capable for cogent expansion say what you mean then label the concept – then you can use the lable. Like this you win a prize for bull-shit bingo
Your Justification
The document is supposed to provide the reader with an accessible basis for running some sort of change initiative that is not a project, yet all you do is make assertions that yield to challenge because they are not supportted by simple illustration of examples. This block could be replaced by “prior thought about what is to be achieved and how improves chances of sucess” – at least this one won’t leave half your readership puzzling about optimised pacing Be clear and honest. It appears to me that the struggle the authorship team experiences to make a ‘program’ into something seperate from a project has eroded your confidence so we experience a flurry of fluffy block of text like this one that obfuscate meaning (aka bullshiting the reader)
Our vote on your recommendation: Rejected
Our justification: We have received your comment on the exposure draft for The Standard for Program Management–Third Edition. No change was made to the text in response to this comment. The review team will not address recommendations that contain profanity.
OriginalText
221 strategy producing better performance, better results, and a sustainable competitive
Your Recommendation
Reword – The use of “better” is a comparative so better than what?
Your Justification
Terms like better left to hang in the air without both sides of the comparison are either sloppy thinking or an advertiser’s attept to sway opinion where no real discriminator exists – If you want to say “xxx is better” then the sentence ends “…than yyyy BECAUSE reason and reason and reason” does opm really work? are there any published surveys? The ones I’m aware of do not show a correlation – positive or negative
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
230 realize specified benefits. Project management develops and implements plans to achieve a
Your Recommendation
Reword or delete to reflect what pgm mgmt is about instead of claiming things that it isn’t about
Your Justification
An enterprise returns utility to shareholders, debtors, workers, customer and society: this duty rests with all those involved in its operations. That duty is overseen by the officers of the enterprise however legally consituted. – They have oblligation to care for benefits as defined by all communities in the short (tactical) and long (strategic) terms Projects deliver change. Within them subject matter expertise combine skills to determine how to create a change to business as usual that matched “what” was requested by those with a duty to sustain capital and return on capital. If you want to add a concept of ‘program’ to the preceeding two truths then (unless you can argue cogently to the contrary and this document does not) program is a control function whose purpose is the aggregation of project control needs that provides inter-project coordination and provides economies of scale by the removal of duplicated controls in each project.
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
243
Your Recommendation
Rewrite the table such that each row expresses a consistent set of concepts that change in nature such that someone looking at an initiative can say “this is project because….” at teh moment any comparison will fit every box on the chart. EG EVERY project manager continiously monitors change in the broad internal/ external environmnent – we don’t capture that their definition of “external” is different. Every PMgr expects change from inside and outside and is prepared for as much as is possible. Every Program manager keeps change managed and controlled
Your Justification
There is no point in including text that does not guide, differentiate, educate or normalise and this tabble does none of these things. It waffles close enough to the target to give an illusion of relevance but it waffles too much to be useful when called upon to assist.
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
257 activities and involves managing the processes at a level higher than those pertaining to
Your Recommendation
replace “pertaining” with simple language
Your Justification
Here and everywhere else the language is outside the core of simple words the chances that readers get lost goes up. We already have a complex topic it is your duty to look for every opportunity to simplify its description – written once and read tens of thousands of times means the effort must be yours to generate the maximum leverage for all those hours spent by readers and the many more spend implementing what they absorb
Our vote on your recommendation: Editorial
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The core committee has reviewed your recommendation and determined that the recommendation is editorial and not substantive. This request will be forwarded to the editorial department for possible inclusion
OriginalText
279
Your Recommendation
Define terms you use – What is a sub-program ? is it a collection of projects withon a collection of projects? Is it a clooection of non-project activity within a program. For that matter define “non-project activity” as may be legitimate within a program
Your Justification
as for “pertains” above – write once read and use many means the duty of clarity is on you to express well – it takes effort to do it well
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, a definition for sub-program will be added to the glossary
OriginalText
312 budget and schedule updates, earned value cost performance reports, change requests and
Your Recommendation
delete “cost”
Your Justification
Applies to all EV assessment and analysis not just cost
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The paragraph has been revised as follows: “Similarly, the program’s benefits delivery, transition, and closing phases provide key data to the portfolio management function. This data may include program status information, program performance reports, budget and schedule updates, earned value and other types of cost performance reporting, change requests and approved changes, and escalated risks and issues.”
OriginalText
317 A portfolio is one of the truest measures of an organization’s intent, direction, and
Your Recommendation
Reword – A portfolio is not a measure. Its contents may be measurable. Perhaps you should say “analysis of a portfolio’s aggregate content will reflect the organisation’s currently agreed strategic intent” But you might also have to say “analysis of the degree of agreement about teh portfolio’s content will reflect the management style of the organisation, the dynamics of its market place and its board’s ability to react in a timely manner”
Your Justification
What is currently written is wrong – a portfolio is not a measure – so the thinking behind the pen is not descriptive, in this case not analytically relaible and so I wonder where else does it say unreliable things that I might later rely upon to guide my duties within organisations. If they suffer do I say “not my fault, I followed their book?” that doesn’t offer equity holders or staff any comfort. What we all expect is that you spend the time to write well
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects individual preference of equal value to what exists.
OriginalText
323
1.4.3 The Interactions Among Portfolio, Program, and Project Management
Your Recommendation
Delete the words and diagram
Your Justification
They simply repeat what has already been written several times in the preceeding 300 lines and drawn in the last 50.
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised.
OriginalText
345 During their life cycle, projects produce deliverables, whereas programs deliver benefits
Your Recommendation
Rewrite the whole guide with a correct and clear view of what your talking about. We are back to the profound crack in your foundations: Every enterprise delivers benefits without any programs. It is the duty of the enterprise’s officers. Wise ones attempt to satisfy as many stakeholders concurrently to the maximum degree possible. Then change comes along and so we need activity that is often labelled “project”. For the officers of teh company the duty to integrate the project’s outputs into operations to deliver benefits was constant. As you’ve written so far “program” is just the business perspective on “project”. Now there may be a beast that deserves the lable program that differentiates it from sinple project but you have yet to isolate what it is that would define it, what actions taht difference would drive, what advantage or consequence their is from describing program.
Your Justification
We need you folk to say what is true and say it well and not to waffle around to appear to fulfil your brief – youve been given a difficult brief – 50 years of current trends has created some memes that are powerful but not in our best interests – your the best hope the rest of us have to turn-around the mistakes that mean management of change is not keeping up with the demands of change in our economies
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this with the committee. Because no recommended text was provided by the submitter, our decision was to leave the content as it stands.
OriginalText
623
2.3.1 Program versus Project Uncertainty
Your Recommendation
Delete and replace with guidance to correctly reflect the reality of uncertainty in program risk management. This section is deeply troubling as it is diametricall opposite in what it says to what it should say. It illustrates a profound misunderstanding of program risk management. Just ask your-selves “is an insurance company subject to more uncertainty because it insures many people or less?” The obvious answer is that the insurance company has almost no risk from the uncertaities that it underwrites due to the increas in the number of uncertaintes the laws of large populations start to apply – Have none of you read Bernstien, understood the difficulties of outliers in project risk. If programs were more unceratin than projects and amplified threat then chief financial officers would long ago have killed them off as a means to enact change.The reality is programs (if they actually exist) provide the means to more economically cover threat impact and increase h eprobability of opportunity realisation because of their greater variety or content and richer interactions over large resource pools. The correct contents for this section includes at least the following, this is incomplete = A program must provide the projects with the a defined, common set of scales for risk assessment so that everyone know what “serious” means in impacts across all program sucess criteria, across proximity and probability terms. The program must accomodate change in assessment as time moves on – eg a 6 week variance (positive or negative) with 52 weeks to respond is different to a 6 week varience with 4 weeks to respond and slip is different to gain (but not necessarily more or less serious) = a program must set the risk management process in place including the means for uncertainties to be escalated to high enough strategc/ financial authority or ‘delegated’ to appropriate technical authorities for design of solutions and or sanction of solutions = each project (a program is only project and program activity) must identify its risks and record them centrally so that a program wide view of repeated or interacting opportunities and threats is visible for cross project aggregation. = THE PROGRAM must look at project risks for common cause, common impact or common responses and may then handle centrally or delegate into a project the handling of a risk (threat or opportunity) on behalf of all program elements = A program must underwrite project threats that are of high impact and low probability by forming contingencies across large number of risks – THIS IS self-insuring = While uncertainty can occur in any axis of program activity it is only risk when its outcomes affect some aspect of the baselines that someone cares about. So the program must define (for example) program critical path so schedule uncertainty can be assessed to deterine if it is schedule risk – using up 6 out of 12 weeks float is not a threat. Keeping resources that would otherwise have been idle busy for an extra 6 weeks may be an opportunity, the costs of the extra resources may be an cost threat – only by knowing te program baseline can project risk be assessed against the program benefits – uncertainties in projects must be assessed vs baselines in the PROGRAM.
Your Justification
We need you folk to publish good guidance and this section isn’t just poorly written its plain wrong, wrong statistically, wrong in practice, wrong
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The references are intended to be representative not all inclusive. However, we will broaden the topic somewhat to be more inclusionary.
OriginalText
629 “progressive elaboration” that constrains and controls uncertainty throughout their life
Your Recommendation
Reword to be correct
Your Justification
Progressive elaboration DOES NOT CONSTRAIN risk, it is a reactive approach to the uncertainty that exists. When we are highly certain we plan (fore-cast, pre-dict) a long way into the future. When uncertainty is high we say-in-advance-our-intended-actions (plan) only a little way. Progressive elaboration is not changing the amount of unknownness in the future You thinking is so wrong I want to cry – we need management of change to be something society is good at and humanity isn’t because of our pyschology. We will never get to dealing with the difficult questions if the most influential guidance is so far off solving the trivial stuff
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The references are intended to be representative not all inclusive. However, we will broaden the topic somewhat to be more inclusionary.
OriginalText
635 modified to fit the environment in which the program is conducted and are unpredictable
636 and difficult to define in advance. This in turn increases the uncertainty, making the
Your Recommendation
Remove teh tautology and sharpen up your thinking and writing
Your Justification
“Unpredictable” means “can not be spoken before the event” as is “difficult to define in advance”. Sometimes saying things twice helps communication by reinforcing a message: as written this in’t one of those times
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. In response to your comment and those of others, we have modified the paragraph read: “This results in an initial program environment that is recognized to be uncertain, and implies the need for a management style that embraces uncertainty in order address it more effectively. Because a program’s approach may be modified during the course of the program to optimize pursuit of its goals, program activities may be observed either to decrease uncertainty, or at times to “uncover” it (leading to perceived increases in uncertainty).”
OriginalText
637 conduct of individual programs distinct and unique. When considering programs in this way,
Your Recommendation
remove tautology
Your Justification
unique must be distinct otherwise it would not be unique
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. In response to your comment and those of others, we have modified the paragraph read: “This results in an initial program environment that is recognized to be uncertain, and implies the need for a management style that embraces uncertainty in order address it more effectively. Because a program’s approach may be modified during the course of the program to optimize pursuit of its goals, program activities may be observed either to decrease uncertainty, or at times to “uncover” it (leading to perceived increases in uncertainty).”
OriginalText
638 it is also clear that programs may include individual component projects that are 100%
Your Recommendation
Think, just for a second what your saying and then rewrite the point to reflect it Nothing (including a project) can be “100% sucessful” if it destroys the investors equity – what you might have meant is a commission may be discharged 1005 to its contract but due to changes in context it no longer returns the benefit the PURCHASER had hoped for. The whole of this publication is partisan to the suppliers perspective and blind to the investor’s perepsective – now that migh be OK if you title the document or explain earlyon that you take only one party’s viewpoint – that would be honest and save you rewriting the whole document – but you cannot publish this as supporting the ethics guide’s stricture of always putting the interests of the investor/ client/ comissioning authority first
Your Justification
As written the sentiment is a nonesense – only the supplier gains in a situation where the customer must pay a bill to discharge a contract where their intended benefit has disappeared. When how you see the world misses a perspective then what you write as guidance misses the same perspective – in this case what you miss is material to your aims
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. In response to your comment and those of other revieers we have modified the paragraph to read as follows: When considering programs in this way, it is also clear that programs may include individual component projects that are entirely successful in achieving their intended delivery; providing outputs, products or services precisely as planned, but in the context of the program’s outcomes and desired benefits, may not contribute at all to the outcomes that were anticipated. This creates additional uncertainty about the results the program may achieve.
OriginalText
646 them individually”, it becomes apparent that cumulative uncertainty is amplified with each
Your Recommendation
AGGGGHHH this is so ignorant Cumulative uncertainty IS NOT AMPLIFIED because these are probabilistic events and the use of a Gausian or Normal distribution becaomes MORE AND MORE relevant – predictability increases – uncertainty decreases
Your Justification
Any text on statistics, any underwriters day-to-day work, and maths grad, any street card-shark, any casino….
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Several comments were received on this section. To reflect the spirit of all comments, this paragraph has been removed.
OriginalText
655
2.3.2 Program Versus Project Change
Your Recommendation
Delete and replace with something credible, balanced and insightful that adds value and is teh vasis for gyuidance
Your Justification
Currently we have something like “The Emperors New Cloths” Program change is different to project change but not like you’ve written here. Project change IS NOT about limiting (L663) change IT IS about propogating the affect of change in one axis of baseline through to the other axis so that authorised decision makers can reassess their benefit equation. As an investor acting across a contract, either “of employment (with staff)” of “for services (with another legal entity” it is my utterly irrepressable right to change anything at any time provided I make appropraite provision and compensation. Change control, whether internal to a legal entity or not is about “what if we…” planning. This is true for everything tha alters any aspect of value generated or timing of value delivery or ost incurred or timing of costs either by action or inaction related to scope (aka quality) or resources applied. ALL change control must therefore be rooted in product creation – projects where what-if planning identifies options for future activity. In a program the nature of the change may decommission, replace or add projects – thats all that is different. In a projet the most extreme change is only to terminate
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The references are intended to be representative not all inclusive. However, we will broaden the topic somewhat to be more inclusionary.
OriginalText
663 stakeholders limit the amount of variance from the planned cost and schedule while
Your Recommendation
If this section as written is salvageable then change “limit” to “balance”
Your Justification
Change management should not limit it should express options
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. In response to your comment and those of other reviewers we have modified the sentence to read as follows: In projects, change management is employed to help the project manager, team, and stakeholders monitor and control the amount of variance from the planned cost and schedule while protecting the approved attributes and characteristics of the planned output.
OriginalText
665 is required that impacts the cost, schedule, or output, then a change request is developed
Your Recommendation
If this section is salvageable add “benefits” before costs
Your Justification
Only for the supplier might cost (revenue and thus profit) be first – for the customer it is benefit that is first in the list of impacts “this change benefits me in such a way … and that is at the consequences of…”
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. In response to your comment and those of other reviewers we have modified the sentence to read as follows: “If a change is required that impacts the benefits, cost, schedule, scope, quality, output (deliverable) or expected benefits, then a change request is developed to modify either the cost, schedule, or intended output (deliverable) of the project.”
OriginalText
672 management to constrain the variance caused by risks and events the project encounters on
Your Recommendation
Replace the scentence with reality instead of an artificial attempt to make-out that program have more distinguishing features than perhaps they do. Your bullshitting us 🙁
Your Justification
Projects constraining change just doesn’t happen in a world where people want to keep their jobs and companies want to keep their customers. More than that very often we sell, either literally across contract or figuratively within the organisation a project at a loss-lead win-the-business price promise and then accentuate every opportunity to introduce change so we can re-apply the pricing mechanics with a new set of dynamics to turn a profit Please get real
Our vote on your recommendation: Rejected
Our justification: We have received your comment on the exposure draft for The Standard for Program Management–Third Edition. No change was made to the text in response to this comment. The review team will not address recommendations that contain profanity.
OriginalText
676 fundamentally different way. Program managers depend on a predetermined, consistent level
Your Recommendation
Replace with correct description of differences
Your Justification
Change only occurs in the cost/ benefit equation, either magnitude or timing (note cost and benefit don’t have to be money). C//B affcts arise from deliverables – outputs created by projects, so can only be created and sized in projects and analysed at program level – since that is where the aggregate benefit is expressed
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
681 contribute positively to the program’s outcome and will not produce negative results. For
Your Recommendation
delete, or expand to be balanced
Your Justification
Assuming positive is a route to disaster – hoping for and promoting positive is sensible but expect negatives to accompany positives is required
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows: For all remaining components, the program manager should require that each will be performed in a manner that will contribute positively to the program’s outcome and will not produce negative results
OriginalText
688 unexpected results—results that may not contribute positively to the intended benefits of
Your Recommendation
Add balance – results always have unexpected affcts – some are also positive
Your Justification
enexpected is not just negative – although humans are more sensative to negative outcomes than equivellently sized positive ones
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows: …but will produce entirely unexpected results—results that may or may not contribute positively to the intended benefits of the program.
OriginalText
693 context of the new environment. When this occurs, the program manager employs change
Your Recommendation
change “new” to “evolving”
Your Justification
improves the meaning of teh guidance offered
Our vote on your recommendation: Accepted With Modification
Our justification: .Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows: …knowing they will not help achieve the desired program benefits if left unattended in the context of the evolving environment.
OriginalText
696 the program’s beneficiaries.
Your Recommendation
Reword to remove the program rar-rar spin. These sentiments apply to any sponsored change whether program or project.
Your Justification
Adding ‘spin’ that presents facts selectively is not true to the ethics guide and makes for untrustworthy guidance.
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this with the committee. Ultimately our decision was to leave the content as it stands.
OriginalText
703 To summarize, projects employ change and change management to constrain or limit the
Your Recommendation
Delete
Your Justification
What is written just is not true
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. The references are intended to be representative not all inclusive. However, we will broaden the topic somewhat to be more inclusionary.
OriginalText
32 broken into more easily managed subprojects. These efforts remain within the discipline of
Your Recommendation
Define the “Sub-” elements We get Subprojects, subprogram (L109), subportfolio (L157), sub initiative (755) so what are they? is a subportfolio a program, a project What? We are told (L-1314) that “program componnts and projects produce individual products” So what is a component that is not a project and produces deliverables!
Your Justification
Vauge terms lead to ambigious guidance. Good guidance avoids ambiguity where possible – this is a case where it is possible to provide definitions
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. While the review team believes the submitter misinterpreted line 30, to ensure clarity for this paragraph, the sentence following this line has been revised as follows: These “programs” include large individual projects or a single large project that is broken into more easily managed subordinate projects. Because these efforts are more accurately characterized as projects, not programs, they remain within the discipline of project management and, as such, are addressed in the PMBOK® Guide. A definition of the term subprogram has also been provided to clarify this point for readers.
OriginalText
362 Organizations address the need for change by creating strategic business initiatives to
363 modify the organization or its products and services. Organizations use portfolios,
364 programs, and projects to deliver these initiatives.
Your Recommendation
Reflect the truth of these observations throught the document
Your Justification
These three lines are good insight
Our vote on your recommendation: Accepted
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Sincere thanks for your positive feedback!
OriginalText
404 Successful business value realization begins with comprehensive strategic planning and
Your Recommendation
Reword – Sucess improves with… it is not a necessity to use strategic planning to realise value
Your Justification
it is not a necessity to use strategic planning to realise value
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
410 program, and project management techniques is essential.
Your Recommendation
change “essential” to “useful”
Your Justification
Value is returned in many circumstances where change (Portfolio, Pgm & Pj) is not involved – indeed change often destroys value
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
432 project management activities by strengthening organizational enablers such as structural,
433 cultural, technological, and human resource practices. By continuously conducting
Your Recommendation
Reword – there are no such things as “…structural…practices” – so what do you mean?
Your Justification
Not clear what is meant as currently written
Our vote on your recommendation: Deferred
Our justification: Thank you for participating in PMI’s public exposure draft process. We truly value your opinion. However, we will defer your recommendation at this time due to a collaborative effort to align and harmonize selected content with other PMI foundational standards. The harmonized content reflects the alignment of multiple standards and the consensus agreement with other standards development committees. In January of 2012, PMI presented the selected harmonized content in another public exposure draft where recommendations were reviewed and changes were incorporated. Since this process was recently performed, recommendations on the harmonized content from this round of public exposure are collected and deferred. Because your recommendation belongs in this category, we are deferring your feedback to the next harmonization cycle. If you would like additional information regarding this process, please contact Quynh Woodward at Quynh.woodward@pmi.org.
OriginalText
461 A program manager should have strong communication skills to interact effectively with
Your Recommendation
reword to emphasise faciltating communications between stakeholders.
Your Justification
The program manager’s role is to get the right people communicating, not to be the principle in every conversation
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects individual preference of equal value to what exists.
OriginalText
466 develop a stakeholder engagement plan to support affected stakeholders, help align their
Your Recommendation
delete “affected”
Your Justification
All stakeholders, by definition are affected (even if their main invovement is to affect)
Our vote on your recommendation: Accepted
Our justification:
OriginalText
480 making decisions, and resolving conflicts and issues. Program managers work with component
Your Recommendation
Reword – maybe “..resolving issues shuch as conflicts.”
Your Justification
better expression of intentions?
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects individual preference of equal value to what exists.
OriginalText
516
2.1 Program Management Performance Domain Definitions
Your Recommendation
Add descriptive elements for delivery of project outputs
Your Justification
A program, if they exist, is a wrapper around a group of changes. Changes are created by projects. Each change can only be some combination of altered/ added/ deleted behaviours, inputs, outputs, processes, or staffing of the organisation – without saying something about these description of “performance domains” is lacks what really counts !
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not reflect a level of detail that is consistent with the remainder of the content in the standard. The role of programs as a business change process is discussed later in Chapter 1 and in Chapter 2.
OriginalText
545
2.1.1 Program Life Cycle Phases Defined
Your Recommendation
Have a profound rethink about what you expect this standard to achieve and who for: this section is a description of A PROJECT from the customer’s perspective
Your Justification
Without clarity of who you are writing for you cannot determine what to write.
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this within the committee. Ultimately our decision was to leave the content as it stands as it defines the topic as good practice on most programs most of the time.
OriginalText
558 progressively elaborate the business or mission statement objectives and expected program
Your Recommendation
Reconsider your model and then write some world enhancing guidance. A phase cannot progressively elaborate the program – progressive elaboration runs across phases. One suggestion of what a program is says that it differs from a project because a project’s end-point is definable at the start while a program’s is not. In this case the program’s scope is progressively elaborated – that is not a phase but a property – In this definition of a program the end may be recognised as having ocurred in hindsight rather than foresight The argument continues that if the end is clearly defined it is a project, but regardless there is no need to progressively elaborate
Your Justification
All we have at the moment is a project from the ‘full-lifecycle’ perspective. If program is to be something where extra insight is required then either that insight is required by/ provided to project customers or the supplier side needs to be reconsidered for what is a program. Another definition of program says it is a group of projects whose outputs are all necessary but none is individually sufficinet to deliver eth benefits – personally I see no distinction here between this “program” and a project which must be a group of work-packages (or phases) all of which are required and none of which is individually sufficient
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “Program definition activities typically occur as the result of a an organization’s plan to fulfill strategic objectives or achieve a desired state within an organization’s portfolio. The primary purpose of the program definition phase is to progressively elaborate the strategic objectives to be addressed by the program, define the expected program outcomes, and seek approval for the program.”
OriginalText
563 • Program Closure—The purpose of this phase is to execute a controlled closure of
Your Recommendation
Rewrite
Your Justification
we are stillin supplier terratory
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects individual preference of equal value to what exists.
OriginalText
563 • Program Closure—The purpose of this phase is to execute a controlled closure of
Your Recommendation
Add descriptions of closure to the document
Your Justification
While the table at L-2417 says that closure is in sections 8.2.3, 8.3.3 – these are omited from the document and thus cannot be reviewed
Our vote on your recommendation: Editorial
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The core committee has reviewed your recommendation and determined that the recommendation is editorial rather than substantive. This request will be forwarded to the editorial department for possible inclusion. The table references will be corrected.
OriginalText
573
Your Recommendation
Redraw to show overlap, remove misrepresentations…
Your Justification
As drawn the diagram is profoundly misleading – they are not sequential Definition happens repeatedly, closure is not (necessarily) of equal size to the other two.
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this with the committee. Ultimately our decision was to leave the content as it stands. The team strongly feels that because operations and other work may be occurring throughout the planning phase, programs may have work in phases occurring on an ongoing or overlapping basis. Gate reviews may be appropriate for project based programs but may not apply when the majority of work is operations based, therefore this comment is rejected.
OriginalText
578 Regardless of duration, all projects follow a similar trajectory. A program is initiated
Your Recommendation
replace “tradjectory” with a meaningful word or phrase
Your Justification
You reduce your communication with non-native english speakers using simiarlies like “tradjectory” – say it plainly not “cleverly”, communicate widely and clearly.
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “Regardless of duration, all programs follow a similar trajectory.”
OriginalText
587 implementation is collectively known as program activities. The names and descriptions of
Your Recommendation
Correct the grammar
Your Justification
use of “is” does not match the plural
Our vote on your recommendation: Editorial
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. The core committee has reviewed your recommendation and determined that the recommendation is editorial rather than substantive. This request will be forwarded to the editorial department for possible inclusion.
OriginalText
590 activity focuses on the individual project and its deliverables while the program risk
Your Recommendation
Correct error or reword for what you mean
Your Justification
Risk planning must focus on consistency across the program, therefore risk planning is a program duty not a project one: risk response planning may be project specific, risk identification is project specific – at least to start with.
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “For example, project risk management activities focus on the individual component projects while program risk management incorporates project-level risks and program-level risks to address the overall risk to the program (see Section 8.4).”
OriginalText
596 support individual program components as the components implement and control their own
Your Recommendation
Correct the sentiment expressed Risk planning flows down, risk ID flows up while the response depends on the nature of the responses – this is similar for other management strategies across projects in the program
Your Justification
Definition of management strategies is a program duty, each then informs the projects of norms and constraints. The other way around leads to chaos
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “Following the same example, results of the individual component project risk planning efforts provide input to the program risk planning effort. Risk control is performed continuously at both the program component level and the program level itself; project level risks may be escalated to the program level or have a cumulative effect that requires the risks to be addressed at the program level.”
OriginalText
2 {ED NOTE: All graphics will be professionally drawn and a References section will be added
Your Recommendation
Do NOT overlap exposure draft review period
Your Justification
Creates too much demand for time availabe
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. However, this is an insufficient recommendation – cannot determine what is being recommended – Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
2 {ED NOTE: All graphics will be professionally drawn and a References section will be added
Your Recommendation
Provide a longet review period
Your Justification
Reading almost 4,000 lines requires 1,300 a week if comments are to be provided in 4 weeks, each 1,000 ines takes over a full day to enter comments – 1 month is not realistic
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. However, this is an insufficient recommendation – cannot determine what is being recommended – Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
2 {ED NOTE: All graphics will be professionally drawn and a References section will be added
Your Recommendation
Provide all the materials
Your Justification
This draft misses 8.2.3 and 8.3.3. How a program transitions into business as usual is a key element of guidance, to omit it reduces or removes the validity of the review process
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We will review and correct the inconsistencies while ensuring the overall flow of the document.
OriginalText
1
The Standard for Program Management
2 {ED NOTE: All graphics will be professionally drawn and a References section will be added
Your Recommendation
Action comments recieved and then provide the next draft for review before proceeding
Your Justification
This document is so far away from world-changing insight & guidance that injection of improvement and repair to the errors will generate a document that is in the ‘ready for review’ state
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
605 the number of programs that exist. Normally, organizations pursue and implement similar
Your Recommendation
Somewhere you must say that while the nature of programs is infinitely varied the people in an organisation and a country and a market-place learn ‘accepted’ pappetrns of response to events – thus HOW programs are managed becomes ‘set in its ways’. Current failure modes are embedded in the current culture, or tone or pattern of responses – a corporate even global ‘script’. Changing the ways people respond is extremely hard both in an organisation and globally. One such potential lever of change would be this document if it was writtn to say teh right, insightful contents instead of invent a bit, mistake a few bits and pretend a bit
Your Justification
That behaviour is learned and scripted is describe in many sources that your document lacks the ability to be world-changing is eveident in the wider collection of comments
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “How much interaction there will be and when it should occur will depends upon the program and its components. The amount of interaction for any given program is as varied as the number of programs that exist.”
OriginalText
608 are similar and often repetitive. Large technology organizations often prescribe domain
Your Recommendation
Make note somewhere (add) that prescribing or constraining business for the convienience of the ICT function is the ‘tail wagging the dog’. ICT is a cost that enables benefit and the business is teh benefit engine so it is the business that should define the trade-offs between freedom and its cost, not ICT technology programs taht should remove choice – they should recommend defined interactions should be limited to defining interfactes or architecture between dissimilar groups to allow implementation freedoms beyond the interfaces
Your Justification
A point of importance that is missing from those presented
Our vote on your recommendation: Rejected
Our justification: ank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects a view of only one particular type of program.
OriginalText
611 intensity. These domains are the areas in which program managers will spend their time
612 while implementing the program. They accurately reflect the higher-level business
613 functions that are essential aspects of the program manager‘s job—regardless of size of
Your Recommendation
Add these sentiments to the role of the program manager section
Your Justification
these observations cross reference where teh PgmMgr’s role description is expanded with details of actions to be taken and objectoves of those actions
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this within the committee. Ultimately our decision was to leave the content as it stands as it defines the topic as good practice on most programs most of the time.
OriginalText
619 characterized as unique and temporary, programs are often large, complex, lengthy, and
Your Recommendation
NO NO NO, Please find meaningful, insightful things to say: Programs and project are both temporary, both unique so this is not a differentiator. If programs are just bigger than projects then there is no disciline to write about outside of teh pmbok guide, if there is a discipline then you have to realy analyse what are the essential differences, what are the consequences of those differences for management activity that directs sucess. Your a million miles off at teh moment. The world havs big projects and small programs so it is not size, the world has simple projects and programs and complex projects and programs so it is not complexity. The world has well defined projects. Is it possible to have a poorly defined project or is that the determinant of program – there is a school of thought taht says so but that would not contradict O’Beng’s well observed “Walking in fog” projet type
Your Justification
This document will get more readership than any other that tried to compete so it really really really must say somethings that are good value and it must say them well – you owe us all a duty of care that to be exercised requires a significant lift in your results so far
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows:: Unlike projects that are characterized as unique and temporary, programs are often large, complex, lengthy, and tend to be less well defined. This section discusses two characteristics that distinguish programs from projects.
OriginalText
718 • Relatedness. A primary consideration that differentiates programs and portfolios
Your Recommendation
Replace to shorten the guidance with “in a program the work included is interdependant such that the intended outcome is dependant on all elements in the scope of teh program. In a Portfolio the work included is related in any way the portfolio owner chooses. Typical groupings are work is resourced by the same resource pool, work delivers to the same client, work is conducted in teh same accounting period. Other groupings are valid – eg conducted in the same geography.
Your Justification
Currently a long way to say not much – bloated standards are worse than slim standards that say as much
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows: In a program, the work included is interdependent such that the intended outcome is dependent on delivery of all elements in the scope of the program. In a portfolio, the work included is related in any way the portfolio owner chooses. Typical portfolio groupings of work include efforts staffed from the same resource pool, work delivered to the same client, or work is conducted in the same accounting period. Other groupings are also valid, for example, work performed within the same geography.
OriginalText
733 the other hand, do not abide by rigid or planned time constraints. The various initiatives
Your Recommendation
Revise to remove teh errors Portfolios divide time by accounting cycles – which are much more rigid than most project event times – but are otherwise ‘endless’ while programs deivide time as dictated by the external pressures of the market place (which includes financial reporting cycles, global fashions, local weather patterns and more) and internal cycles and events driven by project milestones and people’s political desires and constraints
Your Justification
As written this section misrepresents reality
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. In response to your comment and those of other reviewers we have modified the sentence to read as follows: Portfolios, on the other hand, while being reviewed on a regular basis for decision-making purposes, are not expected to be constrained to “end” on a specific date.
OriginalText
734 and work elements defined within portfolios do not directly relate to one another and do
735 not rely on each other to achieve objectives. In portfolios, the organization’s business
Your Recommendation
change ‘objectives’ to ‘benefits’
Your Justification
To deliver an improvement in the global state of the art requires setting the right mindset and mixing that with the will to act. When you write ‘objective’ rather than ‘benefit’ your words have a tiny bit different impact on your readers thinking. Multiply this my millions of conversations and actions and your small actions have huge effect please lets get this guidance right Change is entered into for one of only 2 reasons: involuntarily to protect what we had and voluntarily to gain what we don’t have – it is all about benefits that motivate the genes or memes in our societies.
Our vote on your recommendation: Accepted
Our justification:
OriginalText
742 (projects, subprograms, and activities) that are related in some way and collectively
Your Recommendation
Define “activities”
Your Justification
Writing that lists “activities” without definintion does not provide standardised guidance as to what roles, duties, skills (etc) are being envisaged – EG do activities mean the management of the projects in the portfolio? If so an activity might be “tailor the portfolio governance authorities’s view of how to handle risk to suit the stakeholders and nature of work within a specific program’
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “Programs include work(projects, subprograms, and other work) that are related in some way and collectively contribute to the achievement of the program’s outcomes and intended benefits.”
OriginalText
744 also include the concept of time and incorporate schedules through which specific
Your Recommendation
Reword to align with reality
Your Justification
Every process exists in time, every human endeavor percieves time, some endeavors handle its passage in equal sized units (sized based on the passage of the sun and the moon(c)) while others mark time by events such as the delivery of project outputs
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: “Portfolios do not require the work within the portfolio to be related and are managed in an on-going fashion as initiatives (programs and projects) are introduced to the portfolio and are subsequently completed.”
OriginalText
748 manage a collection of investments and work that are important to the achievement of the
Your Recommendation
YES ! Keep ‘investment’ in mind, go back to line 1 of the document and filter every sentiment by “how is the investment of the bill-payer affected, what behaviour may be present, is desirable, how is the supplier affcted, how will & how should their staff act, what form of contract binds bill-payer and subject matter expert – is it ‘of employment’ or ‘for services’
Your Justification
The current words can be improved by suffusing the writing with the sentiment of line-748
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects a view of only one particular type of program. Investment management is addressed by the Standard for Portfolio Management through which initiatives (programs and projects) are approved and investment (resources) are allocated.
OriginalText
754 organization performs numerous portfolio reviews to evaluate the value generated from each
755 of the projects, programs, and sub initiatives within the portfolio. As the business
Your Recommendation
You must add business as usual as a portfolio element – it is the benefit generating operations taht provide the revenue to support cost-of-capital that is the basis of all investment decisions. Evaluation of the portfolio is always “do we have the capacity to execute the change and what will the future state of the world be after we have made the change”
Your Justification
Your advise is restricted to just the suppliers view of change not teh customer’s view of constancy – we need advise the removes the blinkers
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: During this planning effort, an organization conducts continuous portfolio reviews to evaluate the value generated from the projects, programs, and operational work (business-as-usual) within the portfolio.
OriginalText
756 climate changes, organizations repeatedly evaluate the work of the organization through
757 portfolio reviews, reinforcing components of the portfolio that are in alignment and are
758 achieving intended benefits and organizational objectives while deemphasizing or
759 decommissioning initiatives that are not. New initiatives that have potential for
760 contributing to the overall forward progress and success of the organization are proposed
761 and analyzed during the portfolio review process and create the starting point for new
762 projects, portfolio components, and programs.
Your Recommendation
ABSOLUTELY – so if this re-evaluation of the portfolio make-up is ongoing, and teh projects deliver outputs that the business take into operational benefits delivery do programs exist other than in the business’ normal operation. If a program is the businesses activity that surrounds a project then what we have is a project owner’s guide to compliment the pmbok which is a project supplier’s guide – it is possible that weve now got decent vision of what guidance is needed
Your Justification
As written the PMI manual set is growing in pages and shrinking in usefulness
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects a view of only one particular type of program.
OriginalText
765 perform as desired and align with organizational strategy and objectives. They are
Your Recommendation
clarify wording: something like “their intent aligns with current strategy and their current performance aligns with intent” ?
Your Justification
What is provided is not currently as precise as the words above
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: During an organization’s portfolio review process, programs are evaluated to ensure that they are performing as expected and remain aligned with the organization’s strategy and objectives.
OriginalText
769 starting point typically occurs when the business plan for the program is accepted,
Your Recommendation
AAAGGGGHHHHH NO NO NO The *start* point HAS TO BE before the idea even has two heads discussing it. It is a very blinkered, “supplier”, “projects are temporary” view point taht could ever concive of something starting when so much work has been done and angst suffered that approval to invest in this idea and not another or use resources in revenue-bau activity or return it to shareholders as dividend. PLUS programs are evolutionary, they track an evolving world so resource allocation is (you should be describing the mechanism by which provisions are made) on a flexible, ongoing, drip-feed basis.
Your Justification
This thinking is just big-project supplier – get teh money allocated and then consume it in fees thinking – that isn’t how an investor wants it Consider this: the ideas of “Agile projects” are program management applied on a scale (timewise) between 1/30 and 1/90 of the scale appropriate to a program
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: A concept may be approved for a limited time with limited funding to develop a business case for further evaluation. The business case is then reviewed during the portfolio review process. When the actual program is approved, funding is formally approved and allocated and a program manager is assigned to the initiative.
OriginalText
769 starting point typically occurs when the business plan for the program is accepted,
Your Recommendation
AAAGGGGHHHHH NO NO NO The *start* point HAS TO BE before the idea even has two heads discussing it. It is a very blinkered, “supplier”, “projects are temporary” view point taht could ever concive of something starting when so much work has been done and angst suffered that approval to invest in this idea and not another or use resources in revenue-bau activity or return it to shareholders as dividend. PLUS programs are evolutionary, they track an evolving world so resource allocation is (you should be describing the mechanism by which provisions are made) on a flexible, ongoing, drip-feed basis.
Your Justification
This thinking is just big-project supplier – get teh money allocated and then consume it in fees thinking – that isn’t how an investor wants it Consider this: the ideas of “Agile projects” are program management applied on a scale (timewise) between 1/30 and 1/90 of the scale appropriate to a program
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. To capture the intent and maintain the spirit of all comments, the paragraph or sentence has been revised as follows: A concept may be approved for a limited time with limited funding to develop a business case for further evaluation. The business case is then reviewed during the portfolio review process. When the actual program is approved, funding is formally approved and allocated and a program manager is assigned to the initiative.
OriginalText
779 A key differentiator between program and project management is the strategic focus of
Your Recommendation
Delete or reword There is not a differentiator here – their may be some small variations in emphasis in the short term
Your Justification
I’m sorry, I’ve been trying not to just dismiss sections but this is bullshit. A project may be a tactical response but every project must align to the organisation’s best interests and programs are just collections of projects with their administrative arrangements (like stakeholder engagement) grouped for economy and efficiency. What you should have observed and then said is programs are involved with organisational strategy for a longer time frame than projects – a program is involved in envisioning teh future and creating the future when pre-requisite elements delivered by projects are available for integration and deployment. You cannot say programs are more strategic than the projects on whose backs they stand (or fall).
Our vote on your recommendation: Rejected
Our justification: We have received your comment on the exposure draft for The Standard for Program Management–Third Edition. No change was made to the text in response to this comment. The review team will not address recommendations that contain profanity.
OriginalText
784 In any given organization, there is typically an initiative evaluation and selection
Your Recommendation
remove teh tautology
Your Justification
The section says “select initiatives” twice if not three times
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows: “A key difference between program and project management is the strategic focus of programs. Programs are designed to align with organizational strategy and ensure organizational benefits are realized. To accomplish this, program managers require strategic visioning and planning skills to align program goals with the long-term goals of the organization.”
OriginalText
797 While project managers lead the work on their components, it is the program manager’s
Your Recommendation
Consider “manage” and “lead” and then rewrite to express what you mean
Your Justification
Management and leadership are distinct behaviours. Managers do things right, leaders do the right things. Do you want project managers in a program leading? This is a profound point that needs care to be properly handled. With so many gross errors like the aggregation of uncertainty mis-described as more uncertain rather than tending to a guassian probability function it may be beyond teh current document to address more important but softer issues ike this one – it depends on your desire to take a fee versus provide vlue as to how you decide the disposition of so importat but subtle and hard a topic
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. Numerous comments were received on this section. It has been revised as follows: “While project managers lead and direct the work on their components, it is the program manager’s responsibility to ensure alignment of the individual plans with the program’s goals and intended benefits in support of the achievement of the organization’s strategy. Refer to Chapter 4 for more information on Program Benefits Management.”
OriginalText
797 While project managers lead the work on their components, it is the program manager’s
Your Recommendation
Consider teh role of project sponsor and programme sponsor and then rewrite this section
Your Justification
Someone or some group invests so takes risk in the hope of a reward. Projects are complex trade-offs between actions from a limited resouce pool that follow a path with many choices between certainty of cost and potetial for reward. Each trade-off is a situational decision and must in the final escalation fall to a single authority (individual or committee) who is ‘sponsor’ or sponsor’s delegated authority. How that works for each project in a program, and the potential for give and take across the program’s constituent projects IS a factor of program definition
Our vote on your recommendation: Rejected
Our justification: Recommendation rejected due to content already included elsewhere. The committee considered request but felt that the information requested to be added or changed was already represented elsewhere in the document, specifically lines 1521-1523 in the stakeholders section and 2102-2107 in the governance section.
OriginalText
807 Program planning analyzes available information about organizational and business
808 strategies, internal and external influences, program drivers, and the benefits that
809 stakeholders and intended beneficiaries expect to realize. The program is defined in terms
810 of expected outcomes, resources needed, and the complexity for delivering the changes
811 needed to implement new capabilities across the organization.
Your Recommendation
Delete or reword
Your Justification
What you describe here is project planning for projects with reasonable definition of goal and route to it. Program planning is about creating the monitoring, scouting, reconessance and decision making process by which we pick our route fowards based on the journey so far, the currently visible landscape and our group threat/ opportunity perception.
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this with the committee. Ultimately our decision was to leave the content as it stands.
OriginalText
810 of expected outcomes, resources needed, and the complexity for delivering the changes
Your Recommendation
NOTE “changes” and apply the philosophy that project equals change and program equals interdependant change through the whole documents. But first consider “change to what”, observe it is the current status quo to arrive at a new status quo, recognise that the change, of itself changes the context so the change will change as it evolves. In projects the degree of change may allow us to consider teh contextual status quo to be equivellent pre- and post- change so not to be anything requireing specific management. In a program we might consider teh impact of change to be sufficient that wider consideration is needed – Some have called this “walking on the trampoline” – see surfing the edge of chaos by pascale, millemann, & goija
Your Justification
We need world class guidance from the dominant distributor of words on this subject
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
813 Initiating a program begins by determining the need for a program by the organization or
Your Recommendation
Reword to proprly describe where a program starts
Your Justification
It starts with an idea, often fragile and in competition with other ideas and calls for attention and resources. By the time it is at the stage in L-814 it is a very well developed idea and possible even a finished delivered change
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
819 roadmap provide the right value based on the environment by which the program will be
Your Recommendation
no, this may apply to project, but if program is a meaningful term then best we can hope for is probably that no impediments can currently be seen
Your Justification
If all you do in this guide is re-express project ideas then we you never improve mankinds ability to handle change and since your position is dominant youll hold back everyone else’s improvement and thaht would be counter to the PMI ethics guide, so unless you can improve the guidance to the point where it is clearly beneficial you must not publish it
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We considered this with the committee. Ultimately our decision was to leave the content as it stands.
OriginalText
822
Your Recommendation
add iterative and elaborative nature of the procss to the diagram or delete
Your Justification
as given it is misleading
Our vote on your recommendation: Accepted With Modification
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. We will review and correct the inconsistencies while ensuring the overall flow of the document. The graphic will be updated to ensure it aligns with the remainder of the text
OriginalText
829 Organizational strategy is a result of the strategic planning cycle, where the vision and
Your Recommendation
No The cycle is the result Strategy is the result of interaction between genes and memes, available capital (people and money) and context
Your Justification
As writen youve the cause and effect jumbled and teh real important stuff omitted
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
831 their vision will be achieved. The vision is enabled by the mission that directs the
Your Recommendation
Delete from “the vision is enabled…” to end of scentence
Your Justification
These words have no meaning by the time one reaches the end of teh sentence
Our vote on your recommendation: Accepted
Our justification:
OriginalText
833 initiatives that are influenced by market dynamics, customer and partner requests,
Your Recommendation
Reword to express the real significant determinants and drivers
Your Justification
Yes the market drives change but teh biggest determinants of human reaction to dynamics in he context are: Group think, Regret or resistatnce to change, ability to absorb concurrent changes, capital (people’s skills, will. shared behaviour pattrens and money) and revenue to sevice payroll, dividend and interest costs-of-capital
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Submitter provided insufficient information in the recommended change to allow a review and disposition.
OriginalText
835 may be grouped into portfolios to be executed during a predetermined period. In addition
Your Recommendation
No, reword – they are a portfolio and may be grouped into programs and portfolios
Your Justification
wrong or at least incomplete as written
Our vote on your recommendation: Rejected
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. No change was made to the text in response to this comment. Recommended change does not provide sufficient improvement in the existing text to warrant the change. Reflects individual preference of equal value to what exists.
OriginalText
838 portfolio management to the organizational strategy is to establish a balanced,
839 operational plan that will help the organization achieve its goals and to balance the use
840 of resources to maximize value in executing programs, projects, and other operational
841 activities.
Your Recommendation
YES, YES, YES Reflect this thinkingthrough the rest of the document
Your Justification
portfolios are all about “what is attractive and what can we afford and how do we sequence for a balance or dynamic equilibtium that maximises organisational and societal stakeholder benefit”
Our vote on your recommendation: Accepted
Our justification: Thank you for taking the time to provide feedback on the exposure draft for the Standard for Program Management – Third Edition. And for your positive comments.
No comments yet.