Change Control

TOC

bullet

Change Control

bullet

Syllabus

bullet

CS & MP: Three & 2 Half Distinct Related Themes

bullet

CS3, 4, 8 in Detail

bullet

CC02: Administration of Change Control

bullet

CC 01: The Purpose of Change Control

bullet

CC04: Change Control Technique

bullet

CC04: CS4 Impact Assessment

bullet

CC10: Change Authority

bullet

CC05: Change Control Responsibilities and Activities

bullet

CS3, CS4, CS7 and CS8 Change Control Approach Technique

bullet

CC03 & CM07: Link Between Change Control and Configuration Management
bullet

A15 Issue Log

bullet

A28 Project Issues

bullet

A18 Off-Specification*

bullet

A33 RFC*

bullet

A12 Exception Report

bullet

Exception Plans & Correction

bullet

A11 Exception Plan

bullet

Exception Plans

bullet

Responsibilities in CS Issue, Change or Exception Handling

bullet

DP4 in Detail

bullet

CS & MP Summary

bullet

Change & Issue Log Context

bullet

Change Control Ch20 & Ch23 Fig 23.1

bullet

CO02: Project Issue Records Contents

bullet

Recap & Summary

bullet

Applying PRINCE2®

bullet

Change Control Practitioner Question

Top

Syllabus

bullet

CC 01 describe the purpose of Change Control (p)

bullet

CC 02 identify the products and general administration of Change Control, and understand the content and purpose of a Project Issue, Request for Change, and Off-specification (p)

bullet

CC 03 understand the link between Change Control and Configuration Management (p)

bullet

CC 04 understand the PRINCE2® Change Control Approach technique (p)

bullet

CC 05 understand the Change Control responsibilities and activities of the various PRINCE2® roles within each of the eight processes (p)

bullet

CC 06 create, modify or discuss any of the products of Change Control in a given project scenario

bullet

CC 07 apply Change Control to a given project scenario

bullet

CC 08 apply the Change Control Approach technique to a given project scenario

bullet

CC 09 discuss the factors determining escalation of Project Issues to the Project Board, identify the processes involved and create/discuss the products required, for any given project scenario

bullet

CC 10 discuss the factors affecting the application of the Change Budget and the possible appointment of a Change Authority in any given project scenario

bullet

CC 11 identify the relationship between Change Control and other PRINCE2® components within any given project scenario

Top

CS & MP: Three & 2 Half Distinct Related Themes

Theme three and three point five: Handling Project Issues, & End of Stages (on an Exceptional basis)

Top

CS3, 4, 8 in Detail

Top

CC02: Administration of Change Control

bullet

20.2 Project Issue Management “captures, logs & categorises all Project Issues. Project Issues…may be raised at any time…, by anyone …”

bullet

Steps
bullet

Capture and determine Issue Type (CS3)

bullet

Assessment and formulation of responses (CS4) appropriate to Type
bullet

23.1.3 Six steps

  1. [Identify] What would have to change (including any related products/ secondary impacts)

  2. Assess the effort required

  3. 4, 5 and 6 ! [Assess] Impact on tolerances within plans at all levels, the impact to Business Case and to the risk profile for both customer and supplier

  7!   Reassess priority 23.1.2 Suggests as scale of 1 to 5
        “1: A Must, 2: Important, 3: Nice-to-have, 4: Cosmetic, 5: Not a Change”

bullet

Take action via (CS7 & CS1/MP1 or CS8 & DP4…) then confirm completion

Top

CC 01: The Purpose of Change Control

bullet

Any (All) consideration to alter plans [or any base-lined project element] is managed as a A15 Project Issue

bullet

Provides a single, integrated mechanism for any situation where “what next?” requires challenging the existing plans
bullet

Covers discretionary and non-discretionary changes

bullet

Covers change within tolerance or exceeding tolerance (at any management level)

bullet

20.1 “control of change means the assessment of the impact of potential changes, their importance, their cost and a judgmental decision by management on whether to include them or not
bullet

Approved changes must be reflected in … schedule and budget”

bullet

Fragmented in the manual: Component in chapter 20 & Technique in 23

Top

CC04: Change Control Technique

bullet

23.0 “the control of changes to specialist products, not management products
bullet

“If a product is to be changed, its Product Description should be checked for any necessary changes

bullet

Once a product has been approved, the Project Manager should not authorise any work that would change it without the approval of the Project Board [or delegated change authority]”

bullet

23.1 “All changes [are Project Issues and] use [exactly] the same technique”

bullet

Implemented in the process sequence CS3àCS4àCS5àCS7 or 8
bullet

CS3 just admin (record to Issue Log)

bullet

CS4 analysis

bullet

CS5 PM decision making then

bullet

CS7 correction or CS8 Escalation for Project Board decision making

Top

CC04: CS4 Impact Assessment

bullet

Considers affect of changes on A2 Business Case, A34 Risk & A30+A35 plans

bullet

23.1.3 Change control technique
bullet

Optional impact assessment procedure

bullet

Performed by team members with expertise to make assessment of significance and required response

bullet

20.4 Project Issues [20.4.3 Timescales Costs & Risks] should be viewed against the benefits they offer and their impact on the Business Case]
bullet

Balance the advantage achieved by incorporating the change and the time, cost and risk of implementing it

bullet

20.4.2 The Risk Log
bullet

Project Issues should be considered to identify new risks, any impact on existing risk & check if they are already accounted for

Top

CC10: Change Authority

bullet

20.3 Authority Levels
bullet

“During IP* the Board must consider who is permitted to authorise changes (Project Issues) …to what the Project Board originally committed”

bullet

“May delegate decisions … to a group, here called a ‘change authority’ ”

bullet

Assess Project Issue priority and authorise or reject Project Issues
bullet

23.1.4 Authority level required for decisions based on size & type of response

bullet

Controls the Change Budget

bullet

20.5 H&T “Very often … Project Assurance … act as the change authority.”

bullet

“[in] a programme, programme management define the … authority that the Project Board will have to approve changes”

bullet

PM when with-in stage tolerance and not an approved (baselined) product
bullet

Project Board [or change authority] if within Project Tolerances
bullet

All baselined products require project board’s authority to change

bullet

CoPM if impact to project tolerance

bullet

*IP1 and IP4 are both candidates as IP1 sets up Change Process & IP4 sets up controls (and IP2 decides change budget size!)

Top

CC05: Change Control Responsibilities and Activities

bullet

Change Budget: 20.3.1 An optional budget allocated to the change authority for funding the anticipated level of change
bullet

Avoids each change exceeding tolerance and triggering exception assessments (i.e. without the sequence from CS8àSB6àDP3)

bullet

Responsibility, size & constraints proposed in (IP1?) IP2 & ?IP4

bullet

Agreed with the Board in DP2

bullet

Changes outside the change budget and tolerances will require an Exception Report & may require a request to CoPM

bullet

20.5 H&T “… the Project Board may wish to put a limit on
bullet

(a) the cost of any single change and

bullet

(b) the amount spent on change in any one stage without reference [to themselves]”

bullet

Total impact of changes agreed to date is reported by CS6 in A14 Highlight Report

Top

CS3, CS4, CS7 and CS8 Change Control Approach Technique

Top

CC03 & CM07: Link Between Change Control and Configuration Management

bullet

Change control & Configuration management (CM) are both concerned with control of versions of products and managing baselines

bullet

19.6 "Close liaison [is required]...to identify & control versions of products”
bullet

A baseline is only changed when a Project Issue is authorised by the Change Authority
bullet

20.5 “Procedures used to control Project Issues must be integrated with the configuration management approach…”

bullet

Exceptions caused by Project Issues require a A.24 Product Status Account to assess progress and create A11 Exception Plan

bullet

Configuration management stores the specialist & management products
bullet

I.E. Issue Log and the Configuration Item Records are stored CM

bullet

Both stored in the Project Quality File (Appendix E.3)

bullet

Configuration Item Records cross-reference the A28 Project Issue that gave rise to changes to a product

Top

A15 Issue Log

bullet

An ‘index’ into and summary listing of, the complete set of all A28 Project Issues
bullet

Created in IP5

bullet

Access is controlled by the Configuration Librarian and the use of CS3 and CS4

bullet

CS3 may be used by anyone at anytime to log a new Project Issue of appropriate type

bullet

Composition
bullet

Project Issue number, Issue type & Priority
bullet

Issue Type is one of: A33 Request for Change, A18 Off-Specification, general question or statement of concern

bullet

Author, Date identified & Last updated

bullet

Description

bullet

Status (action taken – if any)

Top

A28 Project Issues

bullet

Generic means to raise (at CS3) either of:
bullet

A Statements of concern, Question or new Risk

bullet

Otherwise use an A33 Requests for Change or A18 Off-Specification

bullet

Raised by anyone at anytime. Then:
bullet

Impact Analysed at CS4,

bullet

Considered at CS5 (and also at CS8 and DP4 if outside project or stage tolerances)

bullet

Actioned at CS7 or SB and DP3 à CS1

bullet

Provides the means to raise & analyse (“in the normal manner” 20.2) a new risk outside of sub-processes dedicated to management of risk

bullet

Composition
bullet

Project Issue number, Author, Date raised & Priority

bullet

Description of the Project Issue

bullet

Analysis of positive and negative impacts on:
bullet

Any & all product A1 Acceptance Criteria

bullet

Project effort, cost, schedule and A34 Risk Log

bullet

Impact on A2 Business Case

bullet

All Plans and all tolerances

bullet

Decision from Project Manager or Project Board as dictated by authorities required

bullet

Signature of decision maker(s) & date

Top

A18 Off-Specification*

bullet

A. 18 Off-Specification
bullet

Warning that a product may/ will/ has failed to meet its A1 Acceptance Criteria in its A22 Product Description
bullet

Often Supplier side & non-discretionary

bullet

Logged in CS3, Assessed in CS4, Actioned in CS5?7 or CS5?8
bullet

Logged by anyone at any time

bullet

May be raised as an A28 and redefined as A18 in CS4

bullet

Composition
bullet

Date & Issue Log number

bullet

Status & Priority assessment

bullet

Description of & Impact of the fault

bullet

Decision

bullet

Allocation details, if applicable

bullet

Date allocated & Date completed

bullet

23.1.4 “the Project Manager may try to solve the problem within the stage tolerance…or if the Board…accept the Off-Specification without corrective action; this is called a ‘concession’”

* CC02: Purpose of Change Records

Top

A33 RFC*

bullet

A. 33 Request for Change
bullet

Requests that a modification to a product or its A1 Acceptance Criteria be considered

bullet

Often customer led and discretionary

bullet

Logged in CS3, Assessed in CS4, Actioned in CS5?7 or CS5?8

bullet

Logged by anyone at any time

bullet

May be raised as an A28 and redefined in CS4

bullet

Composition
bullet

Date & Issue Log number

bullet

Status & Priority assessment

bullet

Description of & Impact of the proposed change

bullet

And of not doing the change

bullet

In measurable terms

bullet

Decision

bullet

Allocation details

bullet

Date allocated & Date completed

bullet

Change to a baselined product always needs the Project Board’s approval
bullet

RFC’s are funded from the project’s Change Budget or cause an Exception

bullet

Impact Analysis is funded from day-to-day project resource allocations

* CC02: Purpose of Change Records

Top

A12 Exception Report

bullet

A. 12 Exception Report
bullet

Record of a forecast deviation beyond tolerance levels within a
bullet

Team plan (project Issue raised at MP2?CS3)

bullet

Stage or Project Plan (CS8)

bullet

Identified from sources external to the project or any of the plans, logs and reports of the project

bullet

Composition
bullet

Description of the cause & consequences of the deviation

bullet

Response options and the effect of each on the A2 Business Case, risks and tolerances

bullet

Escalating manager’s recommended response

Top

Exception Plans & Correction

bullet

Exception Plan requested by the project board DP4?CS8
bullet

Produced by SB6àSB2àSB3àSB4àSB5àDP3 EXA

bullet

Replacement team plan requested by the project manager from team manager

bullet

15.5.5 Exception plan runs from time of exception to the end of the plan it replaces
bullet

May be project (and thus also stage and team) level (SB6 & SB2)
bullet

Approved by CoPM

bullet

Stage (and thus also team) level (SB6)
bullet

Approved by Project Board in DP3 Exception Assessment

bullet

Or just team level
bullet

Managed between project manager and team manager “Following local procedures” (see A.11.2 bp3)

bullet

CS7 Taking corrective action

Top

A11 Exception Plan

bullet

A plan that if approved (by becoming the new baseline) replaces a plan whose contents is no longer desired or relevant
bullet

Sets out the actions from current status/ context to currently desired team/ stage/ project outcome
bullet

Based on recommendations made in an A12 Exception Report (Stage and Project Plan) or Project Issue (Team Plan)
bullet

Resolves the concern raised in the Exception Report

bullet

Approval by the next higher level of the project management team

bullet

Requested as a result of detection and assessment of a tolerance threat*

bullet

Composition.
bullet

Produced according to the product description and plan design of the relevant plan level
bullet

Team plan changes may affect stage plan (with or without impact on stage tolerances)

bullet

Stage plan changes may affect project plan (with or without impact on project tolerances)

bullet

The exception plan may be wholly new or largely the contents of the replaced plan
bullet

Includes all actions to create, quality control and accept relevant products within (possibly revised) scope, risk, benefit, quality, time or cost limits and tolerances

bullet

*Whether Mandatory (eg failure to perform) Discretionary (eg Request for Change) Certain (eg Project Issue) or Uncertain (Risk)

Top

Exception Plans

Top

Responsibilities in CS Issue, Change or Exception Handling

bullet

CS3         Capturing Project Issues
bullet

Project Manager's responsibility

bullet

Project Support/ Configuration Librarian may be central focus for receiving and documenting Project Issues

bullet

CS4         Examining Project Issues
bullet

Project Manager's responsibility

bullet

Team Members may assess impact of Project Issues on products, workload, cost, schedule and risk, and devise alternative courses of action

bullet

Project Support assist with administrative work

bullet

Project Assurance examine impact of Project Issues on the products, risks and the Business Case

bullet

Configuration Librarian maintains the Issue Log

bullet

Change Authority (The Board or a delegated authority) decides actions taken on Project Issues

bullet

CS8         Escalating Project Issues
bullet

Project Manager escalates Project Issues

bullet

Project Assurance monitor situations that could cause a deviation and alert the Project Manager

bullet

Configuration Librarian updates Configuration Item Records

Top

DP4 in Detail

Top

CS & MP Summary

Top

Change & Issue Log Context

Top

Change Control Ch20 & Ch23 Fig 23.1

Top

CO02: Project Issue Records Contents

Top

Recap & Summary

bullet

Any departure from agreed plans or product descriptions is a Project Issue

bullet

All issues are logged in the Issue log using a Project Issue, RFC or Off-Specification

bullet

Every approved or baselined item requires the Board's authority to sanction amendments
bullet

Board may delegate authority to a Change Authority in IP1àDP2

bullet

A change budget may be created (IP2/4àDP2 to forestall every change being an Exception

bullet

Steps are Log(CS3), Impact Assess(CS4), Escalate(CS8-->DP4) or respond(CS7)

bullet

Change control considers amendments to products, Configuration Management stores products therefore two interlinked

Top

Applying PRINCE2®

bullet

CC 06 create, modify or discuss any of the products of Change Control in a given project scenario

bullet

CC 07 apply Change Control to a given project scenario

bullet

CC 08 apply the Change Control Approach technique to a given project scenario

bullet

CC 09 discuss the factors determining escalation of Project Issues to the Project Board, identify the processes involved and create/discuss the products required, for any given project scenario

bullet

CC 10 discuss the factors affecting the application of the Change Budget and the possible appointment of a Change Authority in any given project scenario

bullet

CC 11 identify the relationship between Change Control and other PRINCE2® components within any given project scenario

Top

Change Control Practitioner Question

bullet

Turn to Section:5 Sample Practitioner questions and try question 8
bullet

Part A is a single answer worth either 5 marks or none

bullet

May be worth consulting the Red Book for this one

bullet

The worst I’ve seen was 14 marks or none! Very unfair

bullet

Part B has a “best answer” question worth 0 (wrong), 1(OK) or 2(Best)

bullet

Re-read the scenario S:5.1 if you need to
bullet

There is ‘Additional Information’ specific to Question 8

bullet

Ignore all other ‘Additional Information’ you may have read

bullet

Answer the question using a blank answer grid from S:5.3 then mark your answer using S:5.4

bullet

Research any questions where you disagree with the marking scheme
bullet

How much exam-time was looking up references in the Red Book?