CC03 & CM07: Link Between Change Control and Configuration Management | |||||||||||
|
CC 01 describe the purpose of Change Control (p) | |
|
CC 02 identify the products and general administration of Change Control, and understand the content and purpose of a Project Issue, Request for Change, and Off-specification (p) | |
|
CC 03 understand the link between Change Control and Configuration Management (p) | |
|
CC 04 understand the PRINCE2® Change Control Approach technique (p) | |
|
CC 05 understand the Change Control responsibilities and activities of the various PRINCE2® roles within each of the eight processes (p) | |
|
CC 06 create, modify or discuss any of the products of Change Control in a given project scenario | |
|
CC 07 apply Change Control to a given project scenario | |
|
CC 08 apply the Change Control Approach technique to a given project scenario | |
|
CC 09 discuss the factors determining escalation of Project Issues to the Project Board, identify the processes involved and create/discuss the products required, for any given project scenario | |
|
CC 10 discuss the factors affecting the application of the Change Budget and the possible appointment of a Change Authority in any given project scenario | |
|
CC 11 identify the relationship between Change Control and other PRINCE2® components within any given project scenario |
Theme three and three point five: Handling Project Issues, & End of Stages (on an Exceptional basis)


|
20.2 Project Issue Management “captures, logs & categorises all Project Issues. Project Issues…may be raised at any time…, by anyone …” | |||||||||
|
Steps
|
|
Any (All) consideration to alter plans [or any base-lined project element] is managed as a A15 Project Issue | |||||
|
Provides a single, integrated mechanism for any situation where “what next?” requires challenging the existing plans
| |||||
|
20.1 “control of change means the assessment of the impact of potential changes, their importance, their cost and a judgmental decision by management on whether to include them or not
| |||||
|
Fragmented in the manual: Component in chapter 20 & Technique in 23 |
|
23.0 “the control of changes to specialist products, not management products”
| |||||||||
|
Implemented in the process sequence CS3àCS4àCS5àCS7 or 8
|
|
Considers affect of changes on A2 Business Case, A34 Risk & A30+A35 plans | |||||
|
23.1.3 Change control technique
| |||||
|
20.4 Project Issues [20.4.3 Timescales Costs & Risks] should be viewed against the benefits they offer and their impact on the Business Case]
| |||||
|
20.4.2 The Risk Log
|
|
20.3 Authority Levels
| |||||||||||||
|
“[in] a programme, programme management define the … authority that the Project Board will have to approve changes” | |||||||||||||
|
PM when with-in stage tolerance and not an approved (baselined) product
| |||||||||||||
|
*IP1 and IP4 are both candidates as IP1 sets up Change Process & IP4 sets up controls (and IP2 decides change budget size!) |
|
Change Budget: 20.3.1 An optional budget allocated to the change authority for funding the anticipated level of change
| |||||||||
|
20.5 H&T “… the Project Board may wish to put a limit on
|

|
Change control & Configuration management (CM) are both concerned with control of versions of products and managing baselines | |||||||
|
19.6 "Close liaison [is required]...to identify & control versions of products”
| |||||||
|
Configuration management stores the specialist & management products
|
|
An ‘index’ into and summary listing of, the complete set of all A28 Project Issues
| |||||||||||
|
Composition
|
|
Generic means to raise (at CS3) either of:
| |||||||||||||||||||
|
Raised by anyone at anytime. Then:
| |||||||||||||||||||
|
Provides the means to raise & analyse (“in the normal manner” 20.2) a new risk outside of sub-processes dedicated to management of risk | |||||||||||||||||||
|
Composition
|
|
A. 18 Off-Specification
| |||||||||||||
|
Composition
|
|
23.1.4 “the Project Manager may try to solve the problem within the stage tolerance…or if the Board…accept the Off-Specification without corrective action; this is called a ‘concession’” |
* CC02: Purpose of Change Records
|
A. 33 Request for Change
| |||||||||||||||||
|
Composition
| |||||||||||||||||
|
Change to a baselined product always needs the Project Board’s approval
|
* CC02: Purpose of Change Records
|
A. 12 Exception Report
| |||||||||
|
Composition
|
|
Exception Plan requested by the project board DP4?CS8
| |||||||||||||||
|
15.5.5 Exception plan runs from time of exception to the end of the plan it replaces
|
|
A plan that if approved (by becoming the new baseline) replaces a plan whose contents is no longer desired or relevant
| |||||||||||
|
Composition.
| |||||||||||
|
*Whether Mandatory (eg failure to perform) Discretionary (eg Request for Change) Certain (eg Project Issue) or Uncertain (Risk) |

|
CS3 Capturing Project Issues
| |||||||||||||
|
CS4 Examining Project Issues
| |||||||||||||
|
CS8 Escalating Project Issues
|





|
Any departure from agreed plans or product descriptions is a Project Issue | |||||
|
All issues are logged in the Issue log using a Project Issue, RFC or Off-Specification | |||||
|
Every approved or baselined item requires the Board's authority to sanction amendments
| |||||
|
Steps are Log(CS3), Impact Assess(CS4), Escalate(CS8-->DP4) or respond(CS7) | |||||
|
Change control considers amendments to products, Configuration Management stores products therefore two interlinked |
|
CC 06 create, modify or discuss any of the products of Change Control in a given project scenario | |
|
CC 07 apply Change Control to a given project scenario | |
|
CC 08 apply the Change Control Approach technique to a given project scenario | |
|
CC 09 discuss the factors determining escalation of Project Issues to the Project Board, identify the processes involved and create/discuss the products required, for any given project scenario | |
|
CC 10 discuss the factors affecting the application of the Change Budget and the possible appointment of a Change Authority in any given project scenario | |
|
CC 11 identify the relationship between Change Control and other PRINCE2® components within any given project scenario |
|
Turn to Section:5 Sample Practitioner questions and try question 8
| |||||||||
|
Re-read the scenario S:5.1 if you need to
| |||||||||
|
Answer the question using a blank answer grid from S:5.3 then mark your answer using S:5.4 | |||||||||
|
Research any questions where you disagree with the marking scheme
|